Different connection rules from western Sydney
The Shire is on a different distribution network from Liverpool, Camden and most of western Sydney, and the published approvals differ. On a flexible export connection, a complying system up to 30kW is automatically approved to export up to 10kW per phase. On a fixed export connection the approval is 3kW per system. Anything above 10kW per phase is assessed site by site.
The third rule catches people out. If the property has no reliable internet, exports are held to a static 1.5kW until a connection is available. Coverage is not uniform out towards Heathcote and Waterfall, so we check it at the assessment. A cheap, reliable internet connection is now part of what lets a system export at its full allowance.
- Flexible: up to 10kW per phase, automatic for complying systems to 30kW
- Fixed: 3kW per system
- No reliable internet: static 1.5kW until connected